S
Sue
Situation: I have a report (actually a printed view) that uses a date of
[Status Date] plus 4 weeks. I am using custom task fields to filter the
appropriate tasks.
Issue: I have to manually change the date in the header so that it reads the
correct date of the filter. How do I enter a formula in the header? (such
as ProjDateAdd([Status Date], "4w"). Another option I considered (but
haven't been successful with) is using a calculated custom Project Field.
Any suggestions are welcome.
Thanks,
Sue
[Status Date] plus 4 weeks. I am using custom task fields to filter the
appropriate tasks.
Issue: I have to manually change the date in the header so that it reads the
correct date of the filter. How do I enter a formula in the header? (such
as ProjDateAdd([Status Date], "4w"). Another option I considered (but
haven't been successful with) is using a calculated custom Project Field.
Any suggestions are welcome.
Thanks,
Sue