I have a task that has two resources working on it. R1 and R2. R1 can spend
anywhere between 2 to 4 days on the task, and R2 can spend anywhere between
3 to 8 days on the task.
I could say that the task has a optimistic duration of 5 days, pessimistic
duration of 12 days, and a most likely duration of 8 days. But, how do I get
the resource hours to break up accordingly?
anywhere between 2 to 4 days on the task, and R2 can spend anywhere between
3 to 8 days on the task.
I could say that the task has a optimistic duration of 5 days, pessimistic
duration of 12 days, and a most likely duration of 8 days. But, how do I get
the resource hours to break up accordingly?