G
geoff@activebuddy
Hi:
I'm trying to set up a project plan that I can re-use several times. Once I
complete it, I'll just need to enter a new Project Finish Date, and all of
the tasks will adjust to the new date.
Unfortunately, if I set any constraints on any of the tasks, they will not
move when the new finish date is set. Is there a way to set, for example, a
"finish no later than 90 days before the end of the project" constraint
instead of a "finish no later that 9/1/05" constraint?
Thanks for your help
I'm trying to set up a project plan that I can re-use several times. Once I
complete it, I'll just need to enter a new Project Finish Date, and all of
the tasks will adjust to the new date.
Unfortunately, if I set any constraints on any of the tasks, they will not
move when the new finish date is set. Is there a way to set, for example, a
"finish no later than 90 days before the end of the project" constraint
instead of a "finish no later that 9/1/05" constraint?
Thanks for your help