R
roger
Hi all,
I just found this group and have been eagerly devouring information
that relates to resource allocation (esp. postings by Steve House), but
am still confused by this:
I'm scheduling a 2-hour design meeting with two attendees. I'm setting
this task to Fixed Duration because, as far as I'm concerned, that's
the best way to estimate the project schedule; i.e., I believe it will
take these two people two hours of collaborative work to complete the
design.
When I assign the resources, they are each assigned at 50%, according
to Project's standard algorithm. But this doesn't make sense from my
point of view; I want both people in the room for the entire duration;
I'm extracting two person-hours of work from each. So, I bump their
assigned units to 100%. The work goes to 4 hours, the duration is
unchanged, and all is well. (Another way to do this is to turn off
Effort-driven scheduling when I create the task.)
Now, suppose I schedule the same meeting, but one of the attendees has
only 25% of their time to devote to my project. I've established this
by setting this person's Max units available to 25%. With
effort-driven scheduling turned off, I assign the resources to the
task. The full-time resource is assigned at 100% (2 hours); the
part-time at 25% (.5 hours). But again, this doesn't make sense; I
want the part-time resource to spend 2 hours in this meeting. So, I
bump this person's assigned units to 100%. The work goes to 4 hours,
the duration is unchanged, and all is well..except that the resource is
flagged as overallocated, because their Peak units (100%) exceed their
Maximum (25%).
But this person is actually working just 2 hours, or 25% of the work
day, on my project. How can I tell Project to let me allocate 25% of
this person's day to one task in my project, rather than assuming they
will only do 25% of the work on any given task?
If this is not possible, then I don't see how one can profitably make
use of resource availability when there are tasks with fixed
durations...
Thanks in advance for any insight anyone might provide.
Roger Rohrbach
I just found this group and have been eagerly devouring information
that relates to resource allocation (esp. postings by Steve House), but
am still confused by this:
I'm scheduling a 2-hour design meeting with two attendees. I'm setting
this task to Fixed Duration because, as far as I'm concerned, that's
the best way to estimate the project schedule; i.e., I believe it will
take these two people two hours of collaborative work to complete the
design.
When I assign the resources, they are each assigned at 50%, according
to Project's standard algorithm. But this doesn't make sense from my
point of view; I want both people in the room for the entire duration;
I'm extracting two person-hours of work from each. So, I bump their
assigned units to 100%. The work goes to 4 hours, the duration is
unchanged, and all is well. (Another way to do this is to turn off
Effort-driven scheduling when I create the task.)
Now, suppose I schedule the same meeting, but one of the attendees has
only 25% of their time to devote to my project. I've established this
by setting this person's Max units available to 25%. With
effort-driven scheduling turned off, I assign the resources to the
task. The full-time resource is assigned at 100% (2 hours); the
part-time at 25% (.5 hours). But again, this doesn't make sense; I
want the part-time resource to spend 2 hours in this meeting. So, I
bump this person's assigned units to 100%. The work goes to 4 hours,
the duration is unchanged, and all is well..except that the resource is
flagged as overallocated, because their Peak units (100%) exceed their
Maximum (25%).
But this person is actually working just 2 hours, or 25% of the work
day, on my project. How can I tell Project to let me allocate 25% of
this person's day to one task in my project, rather than assuming they
will only do 25% of the work on any given task?
If this is not possible, then I don't see how one can profitably make
use of resource availability when there are tasks with fixed
durations...
Thanks in advance for any insight anyone might provide.
Roger Rohrbach