Mauro
I need to allocate company vehicles on Project but I'm not sure I'm doing
right.
I create a task and I fix the duration (e.g. 2 days), then I assign 1 person
and 1 vehicle (both are work resources) to the task; automatically the task
duration decreases to 1 day, do I have to re-fix it again on 2 days.
Is there a way to allocate vehicles as work resorces (so handling their over
allocation) without considering their usage on the task duration calculation?
Thanks!