I'm trying to enter vendor capacity constraints in to Project.
In my ramp up I want (say) 120 units delivered per week, but my vendor can
only send me 80 per week (say). Let's say I cut POs 4 weeks before delivery.
I want to order these materials as late as possible and cut POs weekly.
Let's say I need 1200 units in six months.
Any ideas on how I model this in Project?
Thanks!