From project 2003, how can I view resource allocations across multiple
projects? This assumes the same resource is working in all three projects,
and I want to make sure this resource isn't working on three different
projects at the same time. I don't necessarily want to level at this point.

In addition, I want to use a view that is showing the tasks across the
different projects that the same resource is working on. This would be like a
task usage view grouped by project, or something like that. I don't
necessarily want a graph view, since they don't tend to drill down to the
task or assignment level.

Again, this is a proj client purpose. Now, if there is a proj server 2003
method, too, showing tasks and assignments across projects with resource
allocations, that would be great, too (I don't think the analyzer views gives
me all this info, but I could be wrong).

thanks
 
D

Dale Howard [MVP]

Bobby --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the Microsoft Project desktop application only. To answer your question,
use the View Resource Assignments feature, available in the sidepane on the
left side of the Resource Center page. Hope this helps.
 