View the milestones only

A

AlanStotty

Hi,

When I filter by milestones, I also get the main task it is under.

How can I view the milestone lines only?

Thanks in advance.
 
J

JulieS

Hello Alan,

Edit the filter (Project >Filtered For > More filters) and remove the
check from the "Show related summary rows."

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
A

AlanStotty

Hello Alan,

Edit the filter (Project >Filtered For > More filters) and remove the
check from the "Show related summary rows."

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visithttp://project.mvps.org/for the FAQs and additional information
about Microsoft Project









- Show quoted text -

That works well. Thanks.

Also, I can now just use the filter and then go into Options --> View
--> uncheck Show Summary Tasks
 
J

JulieS

AlanStotty said:
That works well. Thanks.

Also, I can now just use the filter and then go into Options --> View
--> uncheck Show Summary Tasks
You're welcome Alan and thanks for the feedback. About the Tools >
Options, View "Show Summary task" option, yes, you can do that.
However, that turns off the display of summary tasks through the entire
project. So if you remove the milestone filter, the summary tasks will
not reappear.

Julie
 