Hi,

Is there a way using MS Project 2003 to view the notes related to a specific
task in another area of the screen?

What I would like to do is to move to a using the keyboard task and be able
to quickly read the notes associated with that task without having to open
the notes.

Thank you,
 
R

Rod Gill

Try:

With a Gantt chart visible select Window, Split
Right mouse click Task form in lower pane and select Task Notes

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
C

Colin

Trauton

As well as Rods suggestion, I usually inset the notes column.

Insert / Column / (field)" Notes"