J
JAWs
I still can't make this feature work. I have SP1, and my Vista and
Office suite is up to date as of yesterday. I created a little
four-task project to help me understand this feature. I created a
resource pool, assigned resources to the tasks, then baselined the
project. I then simulated status sessions, changing current and
status dates and updating progress as if were a real project.
The data looks fine on the tabular reports, but the Visual Earned
Value Over Time Report shows EV and PV to be declining straight lines,
and AC at zero.
Any advice? As an alternative, would anyone who has had success with
this feature be willing to try this report with my file and let me
know if it works in your environment? I need to know if its my system
setup or something I'm doing wrong in the spreadsheet that's causing
the problem.
Thanks,
Jim Williams, PMP
Norfolk, VA
Office suite is up to date as of yesterday. I created a little
four-task project to help me understand this feature. I created a
resource pool, assigned resources to the tasks, then baselined the
project. I then simulated status sessions, changing current and
status dates and updating progress as if were a real project.
The data looks fine on the tabular reports, but the Visual Earned
Value Over Time Report shows EV and PV to be declining straight lines,
and AC at zero.
Any advice? As an alternative, would anyone who has had success with
this feature be willing to try this report with my file and let me
know if it works in your environment? I need to know if its my system
setup or something I'm doing wrong in the spreadsheet that's causing
the problem.
Thanks,
Jim Williams, PMP
Norfolk, VA