Want to change project work without changing duration

P

Perry

Can you please tell me how to change work in microsoft project 2002 without
changing the duration. The project I set up defaulted to setting the
duration; now, I am trying to go back in to adjust the amount of work but it
also changes the duration. For instance, if I have a task that the duration
was set to 2 months, but the amount of work for the resource during that time
is only 2 days, how can I change the work without changing the duration. I
tried setting the project to default at Fixed Duration under schedule options
but that did not work.
thanks
Perry
 
J

Jan De Messemaeker

Hi Perry,

Changing the defauklt does not change the setting on existing tasks
Select all tasks
Look fi rthe "Task information" icon on the toolbar, click it
Advanced tab
Set Task Type to Fixed duration
OK.
Hope this helps
 
P

Perry

Thank you!
Perry

Jan De Messemaeker said:
Hi Perry,

Changing the defauklt does not change the setting on existing tasks
Select all tasks
Look fi rthe "Task information" icon on the toolbar, click it
Advanced tab
Set Task Type to Fixed duration
OK.
Hope this helps
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top