Can you please tell me how to change work in microsoft project 2002 without
changing the duration. The project I set up defaulted to setting the
duration; now, I am trying to go back in to adjust the amount of work but it
also changes the duration. For instance, if I have a task that the duration
was set to 2 months, but the amount of work for the resource during that time
is only 2 days, how can I change the work without changing the duration. I
tried setting the project to default at Fixed Duration under schedule options
but that did not work.
thanks
Perry
changing the duration. The project I set up defaulted to setting the
duration; now, I am trying to go back in to adjust the amount of work but it
also changes the duration. For instance, if I have a task that the duration
was set to 2 months, but the amount of work for the resource during that time
is only 2 days, how can I change the work without changing the duration. I
tried setting the project to default at Fixed Duration under schedule options
but that did not work.