N
Nik003
ok, I'm creating an identical task on two different machines, one connected
to Project Server 2007, and one disconnected (local).
start date: 20/06/2007
duration: 2 days
problem is, when looking at the finish date, I get these results:
disconnected: 22/06/2007 (expected)
connected to PS2007: 23/06/2007 (unexpected)
what's going on here?
to Project Server 2007, and one disconnected (local).
start date: 20/06/2007
duration: 2 days
problem is, when looking at the finish date, I get these results:
disconnected: 22/06/2007 (expected)
connected to PS2007: 23/06/2007 (unexpected)
what's going on here?