J
JustMe
After I created baseline for the project schedule, there are lots of
movement of the task sequence or effort adjustment. The work and
duration delta can be shown, but it becomes irrelevant when too many
movement in the plan.
Is there any guidance on when to re-baseline, and yet be able to refer
back to the original plan if needed?
Thanks.
Frank
movement of the task sequence or effort adjustment. The work and
duration delta can be shown, but it becomes irrelevant when too many
movement in the plan.
Is there any guidance on when to re-baseline, and yet be able to refer
back to the original plan if needed?
Thanks.
Frank