I am creating a Master schedule, that links to 3 individual schedules. I
noticed that in the predecessor field, the path is "C:\Docu...edule.mpp\xxx",
where xxx is the ID of the task that it's linked to. Now, if I
add/delete/move tasks, does that link to the predecessor in the master
schedule get updated? ie. Does the master schedule know where the linked
task is in the new schedule? If it does, then great! But out of curiosity,
how does it know what to link to... by unique ID?