L
LindaC
This seems like it should be simple, but I'm stumped. I have a task with
several predecessors. I would like to know which of those predecessors is
"critical" to that task - in other words, which one of them is determining
the start date of the task. I can look at each of them one by one and figure
it out, but isn't there a way I can get Project to identify it instantly for
me?
several predecessors. I would like to know which of those predecessors is
"critical" to that task - in other words, which one of them is determining
the start date of the task. I can look at each of them one by one and figure
it out, but isn't there a way I can get Project to identify it instantly for
me?