K
Kurt Brockett
The "Who Does What" report is perfect for what I need except for one crucial
piece of info. All of our tasks are a subtask of a larger portion of the
project. Lisitng the individual tasks without the context of the parent
"task category" leaves some odd sounding tasks.
Is there a way to include the parent tasks for the individual task so that
the resource has the entire context?
Example:
I have an "Engineering Tasks" section of tasks.
Say I have tasks 1. Complete code 1. 2. Complete code 2 etc.
When I run the report the assignment only says:
Complete Code 1 <DETAILS DETAILS>.
I want it to be formatted like this:
Engineering Tasks - Complete Code 1 <DETAILS DETAILS> or
Engineering Tasks
Complete Code 1 <DETAILS DETAILS>
etc.
I can provide additional detail if needed.
piece of info. All of our tasks are a subtask of a larger portion of the
project. Lisitng the individual tasks without the context of the parent
"task category" leaves some odd sounding tasks.
Is there a way to include the parent tasks for the individual task so that
the resource has the entire context?
Example:
I have an "Engineering Tasks" section of tasks.
Say I have tasks 1. Complete code 1. 2. Complete code 2 etc.
When I run the report the assignment only says:
Complete Code 1 <DETAILS DETAILS>.
I want it to be formatted like this:
Engineering Tasks - Complete Code 1 <DETAILS DETAILS> or
Engineering Tasks
Complete Code 1 <DETAILS DETAILS>
etc.
I can provide additional detail if needed.