Who Does What Report

T

Todd Gordon

Is there anyway for the WDW report to inculde in the task name the higher
level task it is assigned to.

Thanks!

-Todd
 
J

JulieS

Hi Todd,

The Who Does What report is a tricky one to edit as the assignment
information appearing under the resources' names comes from the
Assignment Schedule checkbox in the details tab of the report
definition. The best work around I can suggest is to create a new table
based upon the Usage table, apply that table to the Resource Usage view,
and print the table portion of the view.

For example:
Display the Resource Usage view and copy the Usage table
(View>Tables>More Tables).

Add the following fields to the default fields in the table:
Task Summary Name (to display the summary task name of the assignment)
Assignment Units (shows in the WDW report)
Delay (shows in the WDW report)
Start (shows in the WDW report)
Finish (shows in the WDW report)

Drag the split bar to the far right to hide the timescaled portion and
print just the table (left side).

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 