Customizing the Who Does What When Report

K

Karin

I need a report that is structured like the who does what when report,
showing the resource name, the task description, deadline & status (ie
started or not started). Is it possible to do this?
Thanks for any assistance!!
 
K

Karin

Sorry, I should have referred to the who does what report, not the who does
what when.
 
J

JulieS

Hi Karin,

The Who Does What When report is based upon the Resource Usage view.
You can likely get close to what you need through printing the view
instead of trying to edit the report. You can add % Work complete field
to the table (left side of the view) as well as Actual Start date field
to see if the assignment has been started or is complete. The task
deadline is more of a challenge as the Resource Usage view shows
resources and assignment information and not task information such as
deadlines.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 