Hi Julie,
I just tested this using Project 2007.
I have a separate Resource Pool file which has 7 projects sharing the
resources in it. I open the resource pool file and the get the "3 options"
message, I opt for the 3rd option, open the resource pool and all the sharer
files in a master project. The master project has all the sub-projects and
the resource pool contained within it. I can run the Who does What When
report and it does show data so I got that wrong, however if I try to run
the "To do List" report the drop down list for "Show Tasks Using" shows no
names, however if you then link the Master Project to the open Resource Pool
the list will show resource names allowing you to run a report for a person
across all projects they are assigned tasks in. So apologies for providing
slightly incorrect information to Gretchen and well spotted Julie. I knew
there was an issue with Reports, Shared Resources and Master Projects but I
guess old age is catching up on me.
--
Dominic Moss
Projectability - Helping People achieve more with Microsoft Project
Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project
www.projectability.co.uk
Why not subscribe to our monthly newsletter for hints tips and views
http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==