Why am I unable to see BCWS values for tasks?

N

nan

I inherited some project schedules. When I view the Earned Value table the
BCWS value for certain tasks are $0. This is despite the fact that resource
costs and work are allocated for the tasks. These schedules are baselined.

Has anyone faced similar problems? How can I resolve them?

Regards
 
G

Gérard Ducouret

Hello,

May be some resource Standard Rates have been set *after * the schedules are
baselined ?

Gérard Ducouret
 
N

nan

Can anything be done to rectify the situation and get a BCWS value? Do I
have to rebaseline?

Regards
 
J

JackD

The second common problem is that the status date is not correct. Go to the
project menu, select project information and see what the status date is set
to. If it is at the beginning of the project then BCWS is by definition = 0.
 
J

JackD

Yes, if you want a baseline with the correct cost information you must set
it now.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top