ProjectNewbie
I have three subprojects and a resource pool. Several tasks only take 1 hour,
however, each of these tasks shows 100% allocation at 1 hour and 300%
overallocation. The work day is 8 hours. My resources each have 5 hours of
time remaining. What am I doing wrong?
however, each of these tasks shows 100% allocation at 1 hour and 300%
overallocation. The work day is 8 hours. My resources each have 5 hours of
time remaining. What am I doing wrong?