Hi eng master,
Are the tasks duplicated on the Resource Usage view? Or the Task Usage view?
Or both?
If you are seeing duplicated task names (actually they are assignments) on
the Resource Usage view and there are multiple resources working on tasks,
this is expected. The assignment (represented by the name of the task
indented under the Resource's name) shows for each resource who is assigned
to the task.
Are you using a resource pool file for your resources? I have frequently
seen assignments repeated in the Resource Usage view when a resource pool
file is used and someone renames (through File > Save As) one of the
projects that is connected to the pool file. The resource pool file then
maintains the connection to *both* project files.
You may want to add the [Project] field to the task usage view to view the
name of the project that the duplicate tasks are coming from. Are they the
*exact* same project name?
Hope this helps. Let us know how you get along.
Julie