nickbike
I have started entering items in a project 2000 Gantt chart view. Then I
flip to the Calendar view and I see I'm viewing Feb 1988. Not very handy, so
I right-click on the calendar and choose "go-to" and i choose today's date.
Ok great. I can now see my tasks in a calendar view.
I go back to the Gannt Chart View to add more tasks, then back to the
calendar view to have a look. The calendar is again looking at Feb 1988, and
I have to right-click and use "go-to" to get to a place where I can view my
tasks. I am thinking I have something set wrong. This is going to drive me
crazy if everytime I flip views it goes back to Feb 1988.
Thanks for your help!
-Nick
flip to the Calendar view and I see I'm viewing Feb 1988. Not very handy, so
I right-click on the calendar and choose "go-to" and i choose today's date.
Ok great. I can now see my tasks in a calendar view.
I go back to the Gannt Chart View to add more tasks, then back to the
calendar view to have a look. The calendar is again looking at Feb 1988, and
I have to right-click and use "go-to" to get to a place where I can view my
tasks. I am thinking I have something set wrong. This is going to drive me
crazy if everytime I flip views it goes back to Feb 1988.
Thanks for your help!
-Nick