Why does the start date change when I import from Excel?

P

Peggy

I am importing an Excel worksheet. The date column has been formated for
date (7/5/06). Once imported into Project, the date shows as 7/4/02. The
dates are consistently off by 4 years and 1 day. Any ideas?
 
M

Mike Glen

Hi Peggy,

Welcome to this Microsoft Project newsgroup :)

Firstly, you shouldn't be importing dates - that's for Project to calculate,
and I suspect that's what's happening. You should enter durations and
predecessors leaving Project to calculates the schedule for you. Have you
set in Project/Project Information your project's Start Date?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 