why is 1 week shown as 4 days?

N

Nina

Whwn i set one tasks duration for 1 week in the start date and finish date it
showd it az only 4 days! and i set all my 7 days of the week as working days.
why?!
 
J

JulieD

Hi Nina

does your definition of a week (tools / options / calendar) match the total
number of working hours that you have made available in your calendar (tools
/ change working time)?
 
J

Jan De Messemaeker

Hi,

Have a look at Tools, Options, Calendar.
Your week is probably defined as 4 times a day.
HTH
 
M

Mike Glen

Hi Nina,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top