Ciarcon
I have a task that is set to 10 days work, Its Fixed Units, with Effort
Driven ticked.
I have allocated 1 resource to this task at 100%.
The allocated resource, using standard calander, also has 4 days none
working time during the period of the task. Hence I would expect work to be
10 days, and duration to be 14 days (10 days for task + 4 days none working
time). Heres the thing, the Gantt bar has changed to reflect this, the
duration field hasnt.
Any Ideas?
I've tried changing to all the task types and checking/unchecking the effort
driven box, all to no avail.
Driven ticked.
I have allocated 1 resource to this task at 100%.
The allocated resource, using standard calander, also has 4 days none
working time during the period of the task. Hence I would expect work to be
10 days, and duration to be 14 days (10 days for task + 4 days none working
time). Heres the thing, the Gantt bar has changed to reflect this, the
duration field hasnt.
Any Ideas?
I've tried changing to all the task types and checking/unchecking the effort
driven box, all to no avail.