A
Ashish
I understand from the project professional documentation that actual
work protected is the duration reported by the resources.
Work is something that i fill in when i create a task.
Does the project makes Work = actual work protected when the task is
100% complete, because on all the completed tasks i see these values as same
Also if this is true, then how would someone figure out difference
between "planned work" and execution ?
any help would be appreciated.
regards
work protected is the duration reported by the resources.
Work is something that i fill in when i create a task.
Does the project makes Work = actual work protected when the task is
100% complete, because on all the completed tasks i see these values as same
Also if this is true, then how would someone figure out difference
between "planned work" and execution ?
any help would be appreciated.
regards