Work Assigned

L

Lucky_guy2000

Is it possible to force Project to break work in specific increments, i.e,
quarters hours vs percent of total work, example:
7 hours for three people
1 - 3.75
2 - 2
3 - 1.25
instead of:
1. 2.33
2. 2.33
3. 2.33
Any help would be appreciated. Thanks.
Johnnie
 
L

Lucky_guy2000

Sorry, should have been more clear.
Other than manually, can I force Project to do as I asked below?
Johnnie
 
L

Lucky_guy2000

Jan,
I know I am just probably grabbing at straws, but can I format the percent
work effort so that work will round up or down to quarter hours?
Johnnie
 
J

Jan De Messemaeker

Hi,

I really don't think so.
Again, my advice is and will always be to enter work instead of percentages.
HTH
 
L

Lucky_guy2000

Jan,
Thanks for all your help. Good to know there are folks out there who can
help.
Johnnie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top