Work doubles "Task doubles per resource"

M

Mike

I have an issue where every resource is showing each task twice when I look
at the resource useage view. Not only does the task show twice but it also
shows that work is schedule for each instance of the task under the resource.
I have been recording actual work performed each and then level the project
by telling project to begin tasks that have not begun after a certain date.

I am using MS Project 2003 SP2 running on Windows XP. I am utilizing a
shared resource pool but so far this is the only project using the resource
pool.

I have tried to clear leveling but it does not remove the duplication of the
task.

How can I fix this.
 
J

Jan De Messemaeker

Hi,

Your pool is connected to 2 copies of your file.
Go into the pool read/write, Tools, Resource Sharing, Share resources,
eliminate the "parasite"
HTH
 