A
AmyD
When I change the duration or work hours for a sub-task the hours for the
main task do not add up to what I have entered below. It will sometimes take
the highest number as its total rather than adding them all up. Or sometimes
it will take part of the sub-tasks and add them up rather than all sub-tasks.
What am I doing wrong? I can't edit the main task headings which is driving
me crazy. Is there not a way to edit those, when I go into the detail they
are gray and I cannot change it. If I could just manually enter the right
total it would help a lot.
Is this possible to manually change the main task durations and work hours?
main task do not add up to what I have entered below. It will sometimes take
the highest number as its total rather than adding them all up. Or sometimes
it will take part of the sub-tasks and add them up rather than all sub-tasks.
What am I doing wrong? I can't edit the main task headings which is driving
me crazy. Is there not a way to edit those, when I go into the detail they
are gray and I cannot change it. If I could just manually enter the right
total it would help a lot.
Is this possible to manually change the main task durations and work hours?