Eric
Hello,
May be my question is already asked but i didn't find it.
I make a project and publish it in MS Project server 2003. I login via the
web access with a team user and I introduce the work done. (for example 2
hours on a 3 days effort task).
I submit.
Then, I login with the Project Manager user and I approve the hours. I save
and then when I look in the Timesheet, I see that the task is 95% complete.
The actual work has changed and I don't see anymore my 2 hours claimed...
An idea ?
Eric