D
DWeb
Hello-
I am seeing something strange that I hope I can explain well enough to see
if someone else has encountered anything similar (and has an explanation!) I
have imported (not linked) data from an Excel worksheet that includes (among
other fields, some custom) task name, work effort (Work, in days), but NOT
duration, start, or end dates (just deadline). I have mapped the fields
appropriately from Excel to Project.
To this project I added a generic resource with varying monthly availability
ranging from around 130% for April 2005 to 1310% in November 2005. This
availability is reflective of an available FTE calculation by month that I
did on a separate Excel spreadsheet.
All of my tasks in Project are setup after importing as Fixed Work, effort
driven. The project start date is 1/17/2005. After importing the tasks, the
somewhat odd thing is that the durations are mostly "1 day?", but some are "0
days?", again, before any resource assignments have been made.
Because my resources are not available until April 2005, I expect that when
I add the generic resource at 100% to a fixed work task of 31 days of work,
that the start date will change to April 1, and that it will calculate to
have a duration of 31 days and a corresponding end date. However, when I
assign "Generic Resource" at 100% and click "Ok", project gives a duration of
thousands of days (ending sometime in 2049), CHANGES the WORK VALUE and the
ASSIGNMENT UNITS to enormous numbers and negative numbers in some cases.
When I change the split view to show Resource Work, I also see that Overtime
Work and Actual Work have also been assigned.
If I delete the assignment, reset the work and the duration and assign
again, the exact same thing happens - every time. Finally, I played with
zeroing out the actual work and overtime work, entering remaining work as 31
days, changing the assigned units back to 100% and after a couple of weird
project calculations, it finally sticks the way I expected it to the first
time.
I can't recreate this issue in a one-task project with a resource that is
not available until April - it works as expected. I suspect something weird
is going on because the tasks were imported, and not entered directly into
Project, but I'm not sure. Needless to say, this is a problem, because I
have a lot of tasks to manipulate and wasn't expecting this to happen.
Any thoughts or suggestions? I hope this made some sense. Thanks!
I am seeing something strange that I hope I can explain well enough to see
if someone else has encountered anything similar (and has an explanation!) I
have imported (not linked) data from an Excel worksheet that includes (among
other fields, some custom) task name, work effort (Work, in days), but NOT
duration, start, or end dates (just deadline). I have mapped the fields
appropriately from Excel to Project.
To this project I added a generic resource with varying monthly availability
ranging from around 130% for April 2005 to 1310% in November 2005. This
availability is reflective of an available FTE calculation by month that I
did on a separate Excel spreadsheet.
All of my tasks in Project are setup after importing as Fixed Work, effort
driven. The project start date is 1/17/2005. After importing the tasks, the
somewhat odd thing is that the durations are mostly "1 day?", but some are "0
days?", again, before any resource assignments have been made.
Because my resources are not available until April 2005, I expect that when
I add the generic resource at 100% to a fixed work task of 31 days of work,
that the start date will change to April 1, and that it will calculate to
have a duration of 31 days and a corresponding end date. However, when I
assign "Generic Resource" at 100% and click "Ok", project gives a duration of
thousands of days (ending sometime in 2049), CHANGES the WORK VALUE and the
ASSIGNMENT UNITS to enormous numbers and negative numbers in some cases.
When I change the split view to show Resource Work, I also see that Overtime
Work and Actual Work have also been assigned.
If I delete the assignment, reset the work and the duration and assign
again, the exact same thing happens - every time. Finally, I played with
zeroing out the actual work and overtime work, entering remaining work as 31
days, changing the assigned units back to 100% and after a couple of weird
project calculations, it finally sticks the way I expected it to the first
time.
I can't recreate this issue in a one-task project with a resource that is
not available until April - it works as expected. I suspect something weird
is going on because the tasks were imported, and not entered directly into
Project, but I'm not sure. Needless to say, this is a problem, because I
have a lot of tasks to manipulate and wasn't expecting this to happen.
Any thoughts or suggestions? I hope this made some sense. Thanks!