Hi all,
If for a specific project you want to work on Saturdays
too, how do you put that in the Project? Our calendar is
standard but we have a project that we have to work on the
weekends too and Project keeps changing the dates and
giving me error messages about the duration and conflicts.
I don’t want to change the Global Template, its only one
project that requires work on Saturdays and Sundays for a
couple of weeks. How do I force Saturdays as working days
to the Project?
Thanks in advanced
Anahita
If for a specific project you want to work on Saturdays
too, how do you put that in the Project? Our calendar is
standard but we have a project that we have to work on the
weekends too and Project keeps changing the dates and
giving me error messages about the duration and conflicts.
I don’t want to change the Global Template, its only one
project that requires work on Saturdays and Sundays for a
couple of weeks. How do I force Saturdays as working days
to the Project?
Thanks in advanced
Anahita