Fei said:
I uses my own customized calendar called MyCalendar1 for my project. In this
calendar I defined 7.5hours/working day. But when I switch Resource Usage
view my tasks are split up in 8hours/working day, why is this?
Fei,
There could be several reasons. When you created your customized
calendar, did you set up the shift hours under "From" and "To",
(Tools/Change Working Time), to total 7.5 hours? If not you need to do
that. Also, if you have any customized resource calendars, they must
also be set up for 7.5 hour shifts.
Changing the Hours per day under Tools/Options/Calendar will only affect
how Project displays days in the Duration field. It does NOT set the
working shift for 7.5 hours.
To properly set up a 7.5, (or any other custom work day), you need to
set both the shift work times and and hours per day to be consistent.
Hope this helps.
John