100% complete help

K

kotoman

2 things really - is there a shortcut key to make a task 100% complete
and is there a cunning way to hide all completed jobs from the task
name column but still have the associated info like time taken/
resources etc in the project file so that I can create reports for
invoicing?

thanks
 
J

Jan De Messemaeker

Yes and Yes
Tools, Customize, Toolbars, Check on Tracking, it has the button.
In teh filyer window (the one showing "AZll Task" select and activate
"Incomplete tasks".
HTH
 