2007 Standard SP1
Fixed units tasks
Question is; when entering actual hours and costs in the task usage view, by
individual resource, strange things happen if zero is entered. Was using MSP
2003 Pro and could easily enter 0 hours if a resource did not work on a task.
the actual hour would translate to the "work" hours for the month. In 2007
it seems if 0 hours is entered, for some resources the assignment is
lengthened, as I would expect, but for other resources the "work" goes
slightly wacko and certainly does not turn to zero for the period as expected.
If something other than zero is entered, everything seems to work fine. Is
this a bug in 2007?
2007 Standard SP1
Fixed units tasks
Question is; when entering actual hours and costs in the task usage view, by
individual resource, strange things happen if zero is entered. Was using MSP
2003 Pro and could easily enter 0 hours if a resource did not work on a task.
the actual hour would translate to the "work" hours for the month. In 2007
it seems if 0 hours is entered, for some resources the assignment is
lengthened, as I would expect, but for other resources the "work" goes
slightly wacko and certainly does not turn to zero for the period as expected.
If something other than zero is entered, everything seems to work fine. Is
this a bug in 2007?