Partially correct.
Default Assignment Owner is a field that exists in Project Server, but
one that is set on resources. This field controls who's My Tasks page
any assignments to this resource shows on by default.
However, this can be overridden in Project Plans. You need to change
the Assignment Owner field for each assignment in Project Pro. This can
be done in the Task Information dialog under the Resources tab or by
adding the Assignment Owner field to one of the Usage Views.
--
Stephen C. Sanderlin
Owner/Founder - EPMFAQ
http://www.epmfaq.com/
http://forums.epmfaq.com/
Principal Consultant - BT INS
http://bt.ins.com/
This electronic message, along with any information, advice, and
opinions it contains, are mine alone and are not representative of my
employer. All information is provided in "GOOD FAITH" and on an "AS IS"
basis only. I provide no presentations or warranties, express or
implied, including implied warranties of fitness for a particular
purpose, merchantability, title, and noninfringement. I strongly advise
you to extensively test any changes, workarounds, or techniques
described herein on a development system prior to implementation in a
production environment, and you are hereby notified that I bear no
responsibility whatsoever for any loss, harm, or otherwise negative
outcomes resulting from your actions, whether or not said actions were
a result of this electronic message, directly or indirectly.