R
Roland67
Project 2003 question...
My project lead has changed tasks within his schedule to 100% in the %
Complete field. However, when he changes the Status Date to a new date some
discrete tasks are changing back to 99% in the % Complete and removing Actual
Finish dates automatically. I checked remaining duration and assignment work
but no hours are past the specified date. Can anybody give me a clue why the
% Complete is reverting back to 99%???
Thanks!
My project lead has changed tasks within his schedule to 100% in the %
Complete field. However, when he changes the Status Date to a new date some
discrete tasks are changing back to 99% in the % Complete and removing Actual
Finish dates automatically. I checked remaining duration and assignment work
but no hours are past the specified date. Can anybody give me a clue why the
% Complete is reverting back to 99%???
Thanks!