J
JNB
Hi all,
A novice question...
What are the definitions of the following dates with respect to the
phases of a project ? Planned date, Scheduled date, Calculated date, Actual
date.
I've seen the following expression in a forum related to Project 2007 for
the definition of FNET constraint:
A novice question...
What are the definitions of the following dates with respect to the
phases of a project ? Planned date, Scheduled date, Calculated date, Actual
date.
I've seen the following expression in a forum related to Project 2007 for
the definition of FNET constraint: