Hi,

I want that when I open any project in project professional .
suppose which have 100 tasks in which 80 tasks are completed and 20 are not
completed.

I want create a group or filter and whatever suitable for this which i set
and when open my that project it will show only incompleted tasks.

regards

micheal
 
J

Jan De Messemaeker

Hi Michael,

With the view that normally opens active click the following menu sequence:
View
More Views
(in the upcoming form) Edit
In teh filter window select Incomplete tasks
OK
Apply

This will do for the active project

Now
Tools
Organizer
Views
In the window for the activeproject select the active view's name
click Copy

Hope this helps
 