Hi,
I want that when I open any project in project professional .
suppose which have 100 tasks in which 80 tasks are completed and 20 are not
completed.
I want create a group or filter and whatever suitable for this which i set
and when open my that project it will show only incompleted tasks.
regards
micheal
I want that when I open any project in project professional .
suppose which have 100 tasks in which 80 tasks are completed and 20 are not
completed.
I want create a group or filter and whatever suitable for this which i set
and when open my that project it will show only incompleted tasks.
regards
micheal