K. Duncan
Before delcaring a task 100% complete be sure that
any "remaining" work is equal to zero.
If you key in an "actual finish" date that is before the
projects current "status" date, it will automatically
assume the task is 100% complete and claim any work that
is remaining in the remaining work field.
any "remaining" work is equal to zero.
If you key in an "actual finish" date that is before the
projects current "status" date, it will automatically
assume the task is 100% complete and claim any work that