actual work

F

Farnaz

Hello
How can I figure out what percentage actual work must have done in specific
time ? and what is the variance between %complete and actual work that has
been done until the specific time?

Any help would be appreciate.

Farnaz
 
G

Gérard Ducouret

Hello Farnaz,
In the Help, look for Earned Value and for the BCWS, BCWP, ACWP fields.
All these calculated fields need a baseline and a Status Date as references.

Hope this helps,
 