Rickey Reynolds
I have a situation that seems simple but I have not been able to make it
work. I have a task say 50 days. Resource one is available immediately and
can start on the task start date. Resources two is not available for say 20
days. After 20 days I want resource 1 and 2 both full time on the project
until its completion. What I seem to be getting is the task is split 25 days
for each resource. Resource 1 stops after 25 days and resource 2 starts on
day 21 and continues on for 25 days. That is not my desired result. I want
both resources working on the project once resource one starts until it is
done.
work. I have a task say 50 days. Resource one is available immediately and
can start on the task start date. Resources two is not available for say 20
days. After 20 days I want resource 1 and 2 both full time on the project
until its completion. What I seem to be getting is the task is split 25 days
for each resource. Resource 1 stops after 25 days and resource 2 starts on
day 21 and continues on for 25 days. That is not my desired result. I want
both resources working on the project once resource one starts until it is
done.