H
Homer
My problem is a very basic one but, I don't know if there is a way to handle
it with MS Project?
Let's think that there is an activity which will start with the start of
another activity. So they should be related SS.
This activity should also only be finished when another activity is
finished. So they must be related FF.
However, if these are not only relations but also constraints for the
duration of our activity then there must be a way to assign these relations
as constraints. It is different than other constraints in MS Project which
can only be set up by date.
The duration in between should be calculated by MS Project automatically in
the backward pass. But, the duration field always waits something from me..
it with MS Project?
Let's think that there is an activity which will start with the start of
another activity. So they should be related SS.
This activity should also only be finished when another activity is
finished. So they must be related FF.
However, if these are not only relations but also constraints for the
duration of our activity then there must be a way to assign these relations
as constraints. It is different than other constraints in MS Project which
can only be set up by date.
The duration in between should be calculated by MS Project automatically in
the backward pass. But, the duration field always waits something from me..