Hi all,
reading through threads it seemed to me that assigning groups of resources
to project task is definitely a common "global" problem and IMHO is quiet
surprising this feature is not part of new Project 2007.

By the way, trying to find out a solution that enable tracking of allocation
for a resource that has tasks assigned both directly and through a group, do
any of you have suggestions on how to solve it programmatically (using VBA
macros) or maybe using enterprise resource pools?

thanks in advance,
 
G

Gérard Ducouret

Hi Nicola,

If you are using the Enterprise resource pool, ie Project Server 2007, have
you tried the Team Assignment Pool feature ?

Gérard Ducouret
 
M

Mike Glen

Hi Nicola,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 