S
stephanie
Finish-to-Start is not working. All my tasks begin on the Project Start
Date. What do I need to adjust?
Date. What do I need to adjust?
Steve House said:Takle a look at the the article "Default Working Hours" in the FAQs on the
MVP web site. It sounds like you changed the entries on the Tools, Options,
Calendar menu rather than the correct "Change Working Time" settings.
Jan De Messemaeker said:Hi,
Here's the misunderstanding: No links apply unles you enter them!
Select teh tasks to be linked, click the "Link Tasks" button!
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
stephanie said:Bingo. I had read the HELP blurb "the default link type is
finish-to-start"
to mean that new tasks are linked f-t-s unless otherwise modified.
Many thanks, Gil!
(if you have time, please look at my problem "Summary Rows," also 8/23.
It's probbly equally simple.)
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.