Allocating work resources across whole project?

L

Lauchlan M

Hi,

say I have a project schedule, and I want to allocate a project manager to
it at 40% time for the duration of the project.

I don't want to constrain this time by start and end dates - I want this
allocation to 'float' in a relative manner when I change the start date.

On top of that, I occasionally want to allocate specific tasks to the PM,
which should come out of the 40%. So if I allocate the PM to specific tasks
at 100% for 5 days, I don't want the PM to be over-allocated at 140% during
these days.

Similarly, I'd like to do the same kind of thing for a support person to
free up developer time - the support person would be allocated at 50% or
100% for the whole project, but still allocated against specific tasks.

What is the best way of approaching these kinds of requirements?

Thx,

Lauchlan M
 
L

Lauchlan M

say I have a project schedule, and I want to allocate a project manager to
it at 40% time for the duration of the project.

I don't want to constrain this time by start and end dates - I want this
allocation to 'float' in a relative manner when I change the start date.

On top of that, I occasionally want to allocate specific tasks to the PM,
which should come out of the 40%. So if I allocate the PM to specific tasks
at 100% for 5 days, I don't want the PM to be over-allocated at 140% during
these days.

Similarly, I'd like to do the same kind of thing for a support person to
free up developer time - the support person would be allocated at 50% or
100% for the whole project, but still allocated against specific tasks.

What is the best way of approaching these kinds of requirements?

Also, if I do this, what are the implications for tracking progress? I guess
I'd like to keep track of the PM or the Support hours used, so I know if I
have some hours up my sleeve to be used later by those resources if needed,
rather than just crossing them off on a time basis.

Any suggestions for the best way to go?

Thx,

Lauchlan M
 
J

Jan De Messemaeker

Hi,

As for the allocation, see my reply to the other question (FAQ 19)
You will have to do the elementary calculation yourself and assign the PM
only 60% to other tasks. Projecy bnever changes assignment units on a task
such as to fit with other tasks.
Hope this helps,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top