S
Shaun
Using Project 2000. What I need is for Project to
tell me how many resources I need to complete a series of
tasks by a certain date. Here is my scenario. The
project starts. From the start milestone there are 15
task lines. Each of these tasks has 8 to 10 tasks
associated with it. These are "Preliminary Design"
tasks. After all 15 are complete there is a review. The
review must happen on a certain date.
I have loaded all of the resource units at 100% and
have entered the hours. Now what I want to do is set the
date for the review and have have project calculate how
many people we need to complete all of these task on
time. I do not want to schedule from the Project finish
date.
Below is a basic example of how my tasks are laid
out. Each line is a different product. After these
preliminary tasks we do the exact same thing again but
but as a detailed design, then again as a final design,
having a review after each phase.
Design - Clean-up - Test - Document
Design - Clean-up - Test - Document
Start Design - Clean-up - Test - Document Review
Design - Clean-up - Test - Documnet
Design - Clean-up - Test - Document
Is it possible for Project to tell me how many people I
need to complete the tasks in time for the review?
Thanks - Shaun
tell me how many resources I need to complete a series of
tasks by a certain date. Here is my scenario. The
project starts. From the start milestone there are 15
task lines. Each of these tasks has 8 to 10 tasks
associated with it. These are "Preliminary Design"
tasks. After all 15 are complete there is a review. The
review must happen on a certain date.
I have loaded all of the resource units at 100% and
have entered the hours. Now what I want to do is set the
date for the review and have have project calculate how
many people we need to complete all of these task on
time. I do not want to schedule from the Project finish
date.
Below is a basic example of how my tasks are laid
out. Each line is a different product. After these
preliminary tasks we do the exact same thing again but
but as a detailed design, then again as a final design,
having a review after each phase.
Design - Clean-up - Test - Document
Design - Clean-up - Test - Document
Start Design - Clean-up - Test - Document Review
Design - Clean-up - Test - Documnet
Design - Clean-up - Test - Document
Is it possible for Project to tell me how many people I
need to complete the tasks in time for the review?
Thanks - Shaun