S
Stephen Moras
Hi guys,
I have a task duration 7 days. I double click on tht Task, and in the Task
Information box go to Resources. I enter 2 resources.
Res 1:100%
Res 2:100%
When i click OK Project doesnt change the duration to 3.5 days. In fact the
duration stays 7 days.
If i do it like this:
Double click on tht Task, and in the Task Information box go to Resources. I
enter 1 resources.
Res 1:100%
Click OK. Duration stays 7 days..makes sense as its only 1 resource.
I then again Double click on tht Task, and in the Task Information box go to
Resources. I enter the 2nd resources.
Res 2:100%
Click OK. Duration changes to 3.5 days..
So from what i have experimented it seems i have to enter the resources 1 by
1 for the Project to amke a change in duration. If i enter a multiple number
of resources in 1 go then Project doesnt make any change.
I am sure i am missing something here. This is too big for it to be a bug.
What am i doing wrong?
I have a task duration 7 days. I double click on tht Task, and in the Task
Information box go to Resources. I enter 2 resources.
Res 1:100%
Res 2:100%
When i click OK Project doesnt change the duration to 3.5 days. In fact the
duration stays 7 days.
If i do it like this:
Double click on tht Task, and in the Task Information box go to Resources. I
enter 1 resources.
Res 1:100%
Click OK. Duration stays 7 days..makes sense as its only 1 resource.
I then again Double click on tht Task, and in the Task Information box go to
Resources. I enter the 2nd resources.
Res 2:100%
Click OK. Duration changes to 3.5 days..
So from what i have experimented it seems i have to enter the resources 1 by
1 for the Project to amke a change in duration. If i enter a multiple number
of resources in 1 go then Project doesnt make any change.
I am sure i am missing something here. This is too big for it to be a bug.
What am i doing wrong?