Having a tough time getting my calendar to switch to 7 hour day per resource.
It shows 8 hours on my "Resource sheet" but 7 hours next to the resource
under the task. Also, the days aren't quite adding up. ie even though it
says 13 calendar days, it is actually 17 on a regular calendar. I've
followed the help menu, but to no avail. Any ideas?