Another Calendar issue

B

Brendon

Having a tough time getting my calendar to switch to 7 hour day per resource.
It shows 8 hours on my "Resource sheet" but 7 hours next to the resource
under the task. Also, the days aren't quite adding up. ie even though it
says 13 calendar days, it is actually 17 on a regular calendar. I've
followed the help menu, but to no avail. Any ideas?
 
B

Bud

Try looking at Tools...Chnage working time and see if the calendar is shaded
monday through friday and using a 7 hour day. Also, check options and make
options match what the calendar says. If the Calendar itself is 7 hours make
sure the options states that as well. They both need to match
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top